A factory books space for ten pallets, but only eight are ready on collection day. Another factory presents all ten, yet the forwarder quotes extra because no cargo can travel on top. Both bills refer to space. One calls for the booking agreement; the other calls for a tape measure, packing photos and the rating terms.
Identify what triggered the charge
Dead freight can arise when the shipper or charterer undertakes to supply a minimum cargo quantity and delivers less. Check the agreed quantity, unit, tolerance, amendment deadline and shortfall rate. Two missing pallets tell you little about the amount due if the agreement is expressed in tonnes or cubic metres.
A non-stackable machine can also take up space above its footprint even when the full consignment arrives. Ask the consolidator how it rated that space and which measured dimensions it used. Overlength, high-density and non-stackable cargo can have separate tariff conditions. Request the applicable thresholds for your route.
Worked example: 100 cubic metres booked, 80 shipped
Assume the contract commits the shipper to 100 cubic metres, allows no tolerance and prices any shortfall at USD 100 per cubic metre. Delivering 80 leaves a shortfall of 20. The example charge is 20 × USD 100, or USD 2,000.
Even if the vessel can carry 200 cubic metres, this shipper committed to 100. Reconcile the agreed quantity, delivered quantity and shortfall rate on one line. If the carrier accepted a reduction before cutoff, use the written amendment when reviewing the invoice.
Measure the finished pallet and check its load rating
Request the final length, width, height and gross weight of each handling unit. Include the pallet base and measure to the furthest projection. A protective frame extending eight centimetres beyond the cartons belongs in the quoted dimensions, even if it holds no product.
For regular cartons, a revised layout may eliminate overhang. Secure the load against movement and ask the packer what weight, if any, the top can support. A flat lid alone tells the forwarder little about its strength. Provide photos and handling limits for fragile machinery or loads with an uneven centre of gravity.
Compare consolidation, LCL and a dedicated container
Several suppliers delivering to one receiver may be able to consolidate at origin. Compare the space saving with warehouse costs and the time spent waiting for the last supplier. If production slips or cargo is damaged before dispatch, give the booking party the revised quantity and obtain written confirmation of any change in cost.
With a full container load (FCL), the shipper normally pays for the container even if part of it travels empty. Compare less-than-container load (LCL) and FCL quotes using the same pickup point, destination and delivery scope. Include handling and space-related charges for LCL, and container haulage and local charges for FCL.
What to send with the quote request
List the final dimensions and gross weight of each pallet, how much top load it can bear, and when it will be ready. Attach front and side photos. Ask the provider to identify the billing unit, minimum commitment, special handling charges and latest date for amending the booking.
For cargo moving from China to Australia or New Zealand, share the packing list with Chinz Logistics to compare options. Mark estimates clearly while packing is under way, then have the quote checked against the finished pallets before collection.